Prefab Case Study: BJC’s Missouri Baptist Sullivan Hospital, Medical Office Building
PROJECT OVERVIEW: Project Name: BJC’s Missouri Baptist Sullivan Hospital,
Medical Office Building
Client: BJC Missouri Baptist
General Contractor: Kadean Construction
TJ Wies Project Manager: Jake Moyers
Location: 751 Sappington Bridge Road, Sullivan, Missouri
Building Type: Medical Office Building Addition
Building Size: 17,287 square feet
Prefabrication Scope: Approximately 11,000 square feet of prefabricated exterior wall panels
Panel Scope: Approximately 8,000 SF of EIFS panels and 2,100 SF of backup panels
Fabrication: 6 weeks
On-Site Installation: 7 days
Schedule Savings: Approximately 6 weeks
Estimated General Conditions Savings: Approximately $61,000